HVAC Submittal

The package of product data, selection printouts and performance figures an HVAC equipment maker sends, through the contractor, to show the engineer that each tagged unit meets the specification and the equipment schedule.

Last reviewed by the OdysseyGPT team

What it is

An HVAC submittal is the package of product data an equipment maker sends for approval before manufacture. For each tagged unit on the equipment schedule it gives a selection printout at the scheduled duty point, performance and sound data, dimensions, electrical and control information and certification evidence, with a list of deviations from the specification at the front.

Key Takeaways

  • The submittal is organised by equipment tag, one selection per scheduled unit.
  • The selection printout must be at the scheduled duty point, not a catalogue rating.
  • The specification section lists what the submittal must contain.
  • Declare deviations at the front. Approval does not excuse an undeclared one.

Why it matters

An HVAC submittal is the set of documents that shows, unit by unit, what a maker intends to supply against a mechanical specification. It is organised by equipment tag. For each air handling unit, chiller, pump, fan or fan filter unit on the schedule there is a selection printout from the maker's software at the scheduled duty point. For an air handling unit that printout states air flow, external static pressure, fan speed and power, coil capacities at the scheduled entering conditions, fluid flow and pressure drops, filter stages, and sound power by octave band. For a chiller it states capacity, power input and efficiency at the scheduled water temperatures, with part-load figures where the specification asks for them. Around the printouts sit fan and pump curves, dimensioned arrangement data with weights and connection positions, materials of construction, motor and electrical data, wiring information, control scope, and options and accessories marked on the catalogue sheets. Certification evidence comes next: a listing under an AHRI or Eurovent programme where the specification names one, filter test reports and declarations. The front of the package should carry a list of deviations from the specification. The contractor passes the submittal to the engineer, who returns it approved, approved with comments or rejected, and makers normally hold manufacture until then. The contract fixes the content and the number of review rounds. A specification section normally has an article listing what the submittal must hold, and that list is the checklist to work to.

How OdysseyGPT uses it

Document Review takes the specification section and equipment schedule as the base and the selection printouts, product data and cover text of your submittal as the documents to check. It reports a status for each requirement with a quote from both sides, and lists the requirements your submittal does not mention. Datasheet Comparison (beta) compares a schedule row with your selection data field by field. OdysseyGPT does not run the selection, read drawings or route the submittal for approval. Engineers decide each status.

Evaluation questions

How do you check an HVAC submittal before sending it?

Take each tag in turn. Compare the selection printout with the schedule row, value by value. Then read the specification section and confirm that each construction, sound, controls, test and document clause is answered somewhere in the package. List what differs on the deviation sheet.

Frequently asked questions

What is a selection printout in an HVAC submittal?

The output of the maker's selection software for one tagged unit at its scheduled duty point. It states the chosen model and components and the calculated performance, such as air flow, pressure, capacity, power and sound.

Is an HVAC submittal the same as a quotation?

No. The quotation is the priced offer made at bid stage. The submittal follows the order and gives the full technical data for approval before manufacture. Deviations declared in the quotation should appear again in the submittal.

What happens if an HVAC submittal is rejected?

The maker corrects the selection or the data and resubmits. Each round costs time against the delivery date, so a check against the specification and schedule before the first submission is worth making.

References

AHRI Certification

Air-Conditioning, Heating, and Refrigeration Institute

The certification programme and the directory of certified product performance.

Visit source

Eurovent Certified Performance: Air Handling Units

Eurovent Certita Certification

Programme scope and the certified casing and performance characteristics.

Visit source