What handover documentation is
Search for a handover document and you mostly find notes for a colleague taking over a job, or the papers given to a building owner. This guide is about a third sense: the documents a manufacturer hands to the customer with a pump, valve, vessel or skid. A project handover, in this sense, is the point where the equipment and its records pass from the manufacturer to the customer, and the customer accepts both.
The equipment is only half of the delivery. The customer needs the records to install it, run it, insure it and prove to a regulator that it was built to the order. Many contracts hold back part of the payment until the handover package is accepted.
Map your documents to the customer's index
Bring one customer index and the approved documents for that order. We map each document to its index line and show you the lines with no document, with two, or with an old revision.
What are the documents needed to hand over?
The exact list comes from the purchase order and the vendor data requirements list. Most equipment orders ask for these groups of project handover documents:
| Group | Typical documents | Who uses it |
|---|---|---|
| Manufacturing record book | Material certificates, welding records, NDE reports, test reports, calibration certificates, signed ITP, nonconformance reports | Customer quality, inspection body |
| As-built engineering | General arrangement and detail drawings at final revision, datasheets, as-built bill of materials, calculations | Customer engineering, site team |
| Operation and maintenance | Installation, operation and maintenance manual, spare parts list, lubrication schedule, special tools list | Operations and maintenance |
| Certificates and declarations | Certificate of conformance, pressure equipment or code documents, declarations required by the destination country | Customer quality, regulator |
| Release and shipping | Inspection release note, packing list, preservation record, open punch list | Logistics, site receiving |
| Agreed changes | Approved deviations, concessions and technical queries | Customer engineering |
The first row is covered in depth in the manufacturing record book guide. You can copy an index from the MRB index template.
Handover package, quality dossier, data book: the names
- Handover package: the whole set of documents delivered with the equipment.
- Quality dossier: the quality records, often the same thing as the manufacturing record book. The term is common in European contracts.
- Manufacturing record book (MRB) or data book: the build and test evidence. See the glossary entry.
- Turnover package: the name used when records pass between project phases. See turnover package.
Customers use these names loosely. Read the contract's definition, and use the customer's own words on your cover sheet and transmittal.
How to create a good handover document set
- Get the customer's index and format rules when the order is placed, not at shipment.
- Turn the index into a tracker: one line per entry, with an owner and the document expected.
- File each record as it is made, under its index number.
- Use approved documents only, and note the revision and approval status on the tracker.
- Before compiling, map every document to one index line and every index line to one document.
- Compile in index order, with the cover sheet, the index and section dividers the customer asks for.
- Send it with a document transmittal and keep the customer's acceptance.
A worked example: mapping documents to the index
The mapping step is where most handover packages go wrong. Here is what it looks like on five index lines.
| Index entry | File mapped | Finding |
|---|---|---|
| 3.1 Material certificates, pressure parts | MTC-heat-48213.pdf and four more | Mapped |
| 4.2 Hydrostatic test report | HT-report-rev0.pdf and HT-report-rev1.pdf | Duplicate: rev 0 is superseded |
| 5.1 General arrangement drawing, as-built | GA-101 rev C, stamped Approved with comments | Unapproved: comments not closed |
| 6.3 Coating inspection record | None | Index entry has no document |
| Not in index | Supplier-catalogue.pdf | Document the index does not list |
Why handover packages come back
- An index entry has no document behind it.
- A superseded revision sits in the package beside the current one, or instead of it.
- A document is still awaiting customer approval.
- The order of the package does not follow the customer's index.
- Extra documents the index does not list, which the customer then has to sort.
- Records that do not link up: a heat number on a part with no certificate behind it. See traceability requirements.
Each return costs a round of comments, a reissue and another wait for the customer's reply. None of these faults needs new testing or new engineering. They are found by reading the index beside the folder, line by line, before the package is sent.
How OdysseyGPT compiles handover documentation against the index
The MRB Compiler (beta) does the mapping step. You upload the customer's index template and your approved documents, and a cover sheet if you have one. It maps each document to its index entry and plans the final record book.
- A compilation manifest: each index entry with the document mapped to it, in index order.
- Findings for index entries with no document, duplicates, unapproved or superseded files, and documents the index does not list.
- A quote from the index and from the document behind each mapping.
- A CSV or JSON export of the manifest.
Document controllers and quality engineers finish the package from the manifest. To find gaps earlier, while manufacturing is still running, use the MRB Readiness Check (beta). For a view of the tools in this area, see MRB software.
Get a manifest for one real order
Send the index template and the document folder for an order near shipment. On the demo you will see the manifest in index order and each finding quoted from your files.
See it on your own documents
Hand over a package that is accepted first time
Choose the order whose handover package worries you most. We map it to the customer's index while you watch, and you leave with the list of entries still to fix.