Handover checklist for an equipment order: format and worked example

A project handover checklist for manufacturers, from the day the order arrives to the day the customer accepts the equipment and its record book.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

This handover checklist is for a manufacturer handing equipment and its record book to a customer, not a shift, job or building handover. List each handover item with an owner, the evidence required and a status. Start it when the order arrives, and close every line before you ask the customer to accept.

Key Takeaways

  • Start the checklist at order stage. Handover problems are set up months before shipment.
  • Every line needs one owner, the evidence that closes it and a status.
  • Use plain status words: present, missing, awaiting approval, wrong revision, incomplete.
  • Handover is finished when the customer accepts in writing, not when the lorry leaves.

What a handover checklist is

Handover checklists exist for shift changes, for staff leaving a job and for new buildings. This one is for a manufacturer. It lists everything that must be true before a customer accepts a pump, valve, vessel or skid and the documents that go with it. It is a working list for the project manager, the quality engineer and the document controller, and it runs for the whole order.

The checklist is not the record book. The manufacturing record book holds the evidence. The checklist tracks whether each piece of evidence, each approval and each shipping step is done. For what the package contains, see handover documentation.

Fill in the document lines of your checklist in one run

Bring the customer's MRB instructions and the folder for a live order. We return every required document with a status, ready to paste into your handover checklist.

Request a demo

Handover checklist format

Use one row per item and these columns. A spreadsheet is enough.

Handover checklist format: the columns
ColumnWhat to writeExample
No.A running numberH-12
ItemWhat must be trueHydrostatic test report accepted by customer
SourceThe clause, index line or ITP step that requires itMRB index 4.2
OwnerOne named personQuality engineer
EvidenceThe document or signature that proves itSigned report HT-031 rev 1
StatusPresent, missing, awaiting approval, wrong revision or incompleteAwaiting approval
DueA date or milestoneBefore final inspection
ClosedDate, and who accepted it18 Nov 2026, customer inspector

Project handover checklist for an equipment order

This project handover checklist follows the order from start to finish. Add or remove lines to suit the contract.

Project handover checklist by stage
StageChecklist itemOwner
At orderCustomer's record book index and format rules received and readDocument controller
At orderVendor document register agreed, with handover documents markedDocument controller
At orderITP approved, with hold and witness pointsQuality engineer
During manufactureMaterial certificates filed as parts arrive, checked against the orderQuality engineer
During manufactureWelding, NDE and heat treatment records filed under their index numbersQuality engineer
During manufactureDeviations and concessions approved in writing and filedProject engineer
Before shipmentAll tests done, reports signed, calibration certificates attachedTest engineer
Before shipmentNonconformances closed, punch list signedQuality engineer
Before shipmentAs-built drawings and datasheets issued at final revisionProject engineer
Before shipmentRecord book complete against the index, and traceability checkedDocument controller
At shipmentFinal inspection passed and release note signedQuality engineer
At shipmentManuals, spares list, packing list and certificate of conformance issuedProject manager
After shipmentRecord book sent by transmittal, customer comments closedDocument controller
After shipmentCustomer's written acceptance of the documentation receivedProject manager

How handover is done

  1. Agree what will be handed over: read the purchase order, the VDRL and the record book instructions.
  2. Build the checklist from those documents, one line per requirement.
  3. Collect evidence as the order runs, and update the status of each line.
  4. Review the checklist before final inspection, and close what is open.
  5. Pass the final inspection and obtain the release.
  6. Ship the equipment, and send the documents by transmittal.
  7. Close the customer's comments and get acceptance in writing.

Status words that make the checklist useful

"Open" and "closed" hide too much. Five status words tell the team what to do next:

  • Present: the document exists, approved, at the right revision.
  • Missing: nothing has been found for this line. Someone must create or obtain it.
  • Awaiting approval: the document exists but the customer or inspector has not accepted it. Someone must chase.
  • Wrong revision: a document is filed, but not the revision the index calls for.
  • Incomplete: part of the evidence is there, such as certificates for some parts and not others.

Common gaps found at handover

  • The customer's index was never requested, so the book was built to the manufacturer's own format.
  • A sub-supplier's certificates arrived late or not at all.
  • A test report is signed by the manufacturer but not by the witness.
  • Drawings in the book are one revision behind the as-built state.
  • A concession was agreed by email and never filed.
  • The certificate of conformance lists a different revision of the specification from the order.

Most of these gaps are document gaps, and all of them are cheaper to close while the order is still on the shop floor. That is why the checklist's document lines deserve a review at each stage, not one read-through in the week of shipment.

How OdysseyGPT runs the handover checklist's document check

The document lines are the slow part of a handover checklist, because each one means opening a folder and reading. The MRB Readiness Check (beta) does that reading. You upload the customer's MRB instructions and your current documentation folder, and the VDRL or MDR and the final index if you have them.

  • Each required section or document, matched to what you supplied.
  • A status for each one: present, missing, awaiting approval, wrong revision or incomplete.
  • A quote from the MRB instructions or index for each requirement.
  • A CSV or JSON export that drops into your checklist.

Your team decides how to close each gap. You can run it as soon as you have the customer's instructions, and again before handover. MRB Traceability Verification (beta) then checks that the records link to each other.

Watch the status column fill itself in

Give us one order's instructions and folder. During the demo you will see each index line get its status and the quote behind it, and you take the export away.

Request a demo

See it on your own documents

Close the handover checklist before the customer opens the book

Pick the order nearest to shipment. We check its documents against the customer's instructions on the call and show you what is still open.

Request a demo

Frequently asked questions

How is handover done?

For an equipment order, handover is done in steps. Agree with the customer what will be handed over, build a checklist from the order and the record book instructions, collect evidence during manufacture, pass final inspection, ship the equipment, send the documents by transmittal, close comments and obtain the customer's written acceptance.

What is an example of a checklist?

A handover checklist line might read: item H-12, hydrostatic test report accepted by the customer, required by MRB index 4.2, owner the quality engineer, evidence report HT-031 revision 1, status awaiting approval, due before final inspection. Each line names what must be true, who owns it and what proves it.

What are the typical items included in a building handover checklist?

A building handover checklist usually covers as-built drawings, operation and maintenance manuals, warranties, test and commissioning certificates, keys and a snag list. An equipment handover checklist covers similar ground for one manufactured item: as-built drawings, manuals, the manufacturing record book, test reports, the certificate of conformance and a signed punch list.

What are some good checklists for project management on an equipment order?

Four checklists carry most of an order: an order acknowledgement checklist at the start, a pre-inspection checklist before each customer visit, a FAT readiness checklist before the acceptance test, and a handover checklist that runs throughout. Each one lists the item, its owner, the evidence and a status.

When should I start the handover checklist?

Start it when the order arrives. The customer's record book index and document requirements are set in the purchase order, and records are far easier to file as they are made than to find later. A checklist started at shipment only tells you what is missing when it is hardest to get.