Deviation request and concession request: the difference, with a form

When to raise each one on an engineered-equipment order, what the form must contain and how to get it approved.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

A deviation request asks the customer's permission to depart from a specified requirement before the item is made. A concession request asks permission to use or release an item that has already been made and does not conform. Both need the requirement, the proposed departure, a justification and a written customer decision.

Key Takeaways

  • Deviation request: before manufacture. Concession request: after a non-conformance exists.
  • Both are permissions for a stated scope. Neither changes the specification itself.
  • A request without the exact clause and a technical justification is usually sent back.
  • Deviations agreed at tender should be in the order, so they never need a request later.

What is a deviation request?

A deviation request is a formal request to depart from a specified requirement before the work is done. This guide covers its use on engineered-equipment orders, where a manufacturer asks its customer to accept something different from the specification, drawing or standard named in the order. The same phrase appears in other fields, such as government grants and airline bookings, which are not covered here.

A concession request is the sister document. It is raised after the event, when an item has been made or tested and found not to conform, and the manufacturer asks to use it, repair it or release it as it is. Some customers call this a waiver.

See which deviations your offer already contains

Bring the customer's requirements and your technical offer from one order. We list every deviation with a quote from both documents, so each request can be raised before manufacture and not after.

Request a demo

Deviation request vs concession request

Deviation requestConcession request
WhenBefore manufacture or before the affected step.After a non-conformance has been found.
What it asksPermission to depart from a requirement.Permission to use or release a non-conforming item.
Usual triggerA requirement cannot be met as written, or a better alternative exists.An inspection or test result outside its requirement.
ScopeA stated quantity, tag list or period.The specific items affected, by serial or heat number.
Linked recordTechnical deviation list, technical query.Non-conformance report.
Customer's positionCan still say no at low cost to both sides.Saying no means rework, replacement or delay.

The quality vocabulary in ISO 9000 draws the same line. It uses the term deviation permit for permission given before a product is made, and concession for permission to use or release one that does not conform.

RFD and engineering deviation request: the same idea under other names

  • What is an RFD? RFD stands for request for deviation. It is the name used in defence and aerospace contracting for a deviation request: permission, asked for in advance, to supply items that do not fully meet a requirement, for a stated number of units or period.
  • What is an engineering deviation? It is a temporary, approved departure from a drawing, specification or process, approved by engineering. An engineering deviation request is the form that asks for it.
  • What is a deviation form? It is the document that carries the request: the requirement, the proposed departure, the reason, the effect and the approval signatures.
  • A technical query asks a question. If the answer changes what you supply, a deviation request usually follows.

Deviation request form, field by field

Copy these fields into your own deviation request form. The same form serves as a concession request with the extra fields at the end.

Deviation request form fields
FieldWhat to write
Request number and revisionA unique number from your register.
Request typeDeviation (before manufacture) or concession (after).
Order and itemPurchase order number, equipment tag, part number and quantity affected.
RequirementDocument number, revision and clause, with the requirement in the customer's words.
Proposed departureExactly what you will do or have done in its place.
ReasonWhy the requirement cannot be met, or why the alternative is offered.
Technical justificationWhy the result is still fit for service, with calculations, test data or code references attached.
EffectAny effect on performance, interchangeability, safety, documents, delivery and cost.
ScopeWhich items or which period the permission covers.
Supplier approvalName, position, signature and date.
Customer decisionAccepted, accepted with conditions or rejected, with name, signature and date.
Concession only: non-conformance referenceThe NCR number and the measured or tested values.
Concession only: proposed dispositionUse as is, repair or rework, and any re-inspection.

To keep the requests in one list, use the technical deviation list template.

Worked example: one deviation and one concession on a valve order

Deviation request. The customer's specification asks for a coating system the manufacturer does not apply. Before production starts, the manufacturer raises a deviation request. It quotes the coating clause, proposes its qualified system, attaches the system's test data and states that there is no effect on delivery. The customer accepts with one condition, a thicker final coat, and the condition is written into the inspection and test plan.

Concession request. During final inspection, the face-to-face dimension of one valve is found slightly outside the tolerance on the approved drawing. An NCR is raised. The manufacturer then raises a concession request for that serial number. It gives the measured value and explains the effect on installation. The customer reviews its piping and accepts use as is for that one valve. The concession goes into the manufacturing record book.

How to get a deviation request approved

  1. Raise it early. A request made at tender or order stage is the easiest to approve.
  2. Quote the exact clause and revision. Do not paraphrase the requirement.
  3. State the departure in one sentence a reader can check.
  4. Attach the evidence. A justification without data invites a question.
  5. State the scope, so the customer knows it does not apply to everything.
  6. State the effect on cost and delivery, even when it is none.
  7. Get the decision in writing and file it where inspection and handover can find it.

The best request is the one you never have to raise during production. Deviations listed in the offer and accepted in the order are already agreed. See the technical deviation list guide.

How OdysseyGPT does this check

The Deviation Register (beta) finds the deviations before they turn into concessions. It reads the customer's requirements with your proposal, technical offer and clarification replies, and merges new findings against your existing register if you have one.

  • One line per deviation, with the requirement, your position and a quote from each source.
  • Declared deviations, undeclared deviations, qualified responses and deviations raised in clarifications.
  • Technical, commercial and documentation consequences for each line.
  • A risk level and a review state, so you can see which lines still need the customer's decision.
  • A CSV or JSON export.

Each line already holds the first fields of the request form: the clause, the customer's wording and your position. Your engineers add the justification and send the request.

Turn one offer into a list of requests to raise

Send the customer's specification and your offer for an order in progress. On the call you will see each deviation with its quotes, its risk level and whether the customer has decided on it yet.

Request a demo

See it on your own documents

Raise deviation requests early, with the clause already quoted

Bring one order's requirements, your offer and the clarification replies. We show you the register that comes out and how each line maps onto your deviation request form.

Request a demo

Frequently asked questions

What is a deviation request?

A deviation request is a formal request for permission to depart from a specified requirement before the affected item is made. It states the requirement, the proposed departure, the reason, the technical justification and the scope. The customer or design authority accepts it, accepts it with conditions or rejects it in writing.

What is an RFD request for deviation?

RFD stands for request for deviation. The term is common in defence and aerospace contracts. It is a request, made in advance, for permission to supply items that do not completely meet a specification or drawing requirement, for a stated number of units or a stated period. The design itself is not changed.

What is a deviation form?

A deviation form is the document used to request and record a deviation. It holds the order and item details, the requirement with its clause, the proposed departure, the reason and justification, the effect on cost and delivery, the scope, and the signatures of the supplier and the approving customer.

What is an engineering deviation?

An engineering deviation is a temporary, approved departure from a drawing, specification or process. It applies to a stated quantity or time and is approved by the responsible engineering function, and by the customer where the order requires it. A permanent change is handled by a design or engineering change, not a deviation.

Is a concession the same as a waiver?

In most companies, yes. Both words describe permission to accept an item that has already been made and does not conform, either as it is or after repair. Concession is the term in the ISO quality vocabulary. Waiver is common in defence and aerospace contracts. Check which word your customer's contract uses.

References

ISO 9000:2015 Quality management systems. Fundamentals and vocabulary

International Organization for Standardization