Bid leveling: how to compare vendor bids like for like

What it means to level a bid, a bid leveling sheet you can copy, and a worked example for equipment vendor offers.

By Ademola Afolabi, Founder, New Odyssey Ltd · Last reviewed:

The short answer

Bid leveling means adjusting competing bids so they cover the same scope, terms and specification before you compare prices. The term comes from construction. For equipment vendors it has two parts: technical leveling, which finds what each offer deviates from or leaves out, and commercial leveling, which prices those differences.

Key Takeaways

  • A bid is level when it covers the same scope, on the same terms, to the same specification as the others.
  • Level the technical content first. A price means little until you know what it buys.
  • Record every adjustment and where it came from, so the award can be explained.
  • On equipment enquiries, silence in an offer is a gap to clarify, not agreement.

What bid leveling means

Bid leveling is the work of making bids comparable. This guide covers the engineered-equipment sense: a buyer or project engineer comparing vendor offers for a pump, valve, vessel or skid against one specification. In construction the same word describes a general contractor comparing subcontractor bids. British writers spell it bid levelling.

What does it mean to level a bid? It means removing the differences that are not about price. One vendor includes freight and another leaves it out. One offers the specified material and another offers an alternative. You adjust or clarify each difference until every bid describes the same thing. Only then do the prices tell you who is cheaper.

See the technical leveling done for you

Bring one specification and the vendor offers you received against it. We show you every deviation, gap and qualified answer in each offer, with the page it came from.

Request a demo

The two halves of leveling an equipment bid

Technical levelingCommercial leveling
QuestionWhat has each vendor really offered?What does each offer really cost?
ReadSpecification, datasheets, exceptions lists, covering letters, clarification replies.Price sheets, terms, delivery, options and exclusions.
OutputDeviations, gaps and clarification questions for each vendor.An adjusted price for each vendor on the same basis.
Done byProject and package engineers.Buyers and procurement.

The technical half is a technical bid evaluation. The commercial half ends in a bid tabulation. Bid leveling is the bridge between them.

How to level bids, step by step

  1. Fix the baseline. List the requirements from the enquiry: scope of supply, specification, datasheet, documents, tests, delivery and terms.
  2. Read each offer against the baseline, one vendor at a time. Mark each requirement as met, deviated, qualified or not mentioned.
  3. List the exclusions and additions. Note anything a vendor priced that the others did not, and anything it left out.
  4. Send clarification questions. Ask each vendor to confirm, withdraw or price each open point.
  5. Adjust the prices. Add the cost of missing scope and take out options nobody else offered. Use the vendor's own figures where you can.
  6. Record the reason and the source for each adjustment.
  7. Compare the leveled totals and write the recommendation.

A bid leveling sheet you can copy

A bid leveling sheet has one column per vendor and one row per item. Use these rows as a bid leveling template and add your own package-specific lines.

Bid leveling sheet for an equipment package
RowWhat to record for each vendorWhy it matters
Base priceThe quoted price and its currency and validity date.The starting point before any adjustment.
Scope of supplyEach main item: included, excluded or optional.Missing items are the most common reason for a low price.
Technical deviationsEach exception to the specification, with the clause.A deviation may lower the vendor's cost or raise yours.
GapsRequirements the offer never mentions.They need a question before you can rely on them.
Inspection and testingWitnessed tests, hold points and third-party inspection included or not.Testing is often priced as an option.
DocumentationVendor data and record book included to the enquiry's list.Document scope differs widely between vendors.
DeliveryDelivery time and delivery terms.Different terms move freight and risk between the parties.
Payment and warrantyPayment milestones, guarantees and warranty period.They change the real cost of the offer.
AdjustmentsEach amount added or removed, with its reason and source.This is the record that defends the award.
Leveled totalBase price plus adjustments.The figure you compare.

Prefer a file? Start from the bid tabulation template or the technical bid evaluation template.

Worked example: three offers for one pump package

A buyer receives three offers for a centrifugal pump package. Vendor A has the lowest price. Reading the offers against the specification shows why.

What reading the offers found
ItemVendor AVendor BVendor CLeveling action
Baseplate and coupling guardExcluded in the covering letterIncludedIncludedAsk A for a price and add it.
Witnessed performance testNot mentionedIncludedOffered as an optionClarify with A. Add C's option price.
Mechanical seal materialAs specifiedAlternative offeredAs specifiedSend B's alternative to engineering for a decision.
Painting specificationVendor standardAs specifiedAs specifiedDeviation for A. Ask A to price the specified system.
Vendor documentsPartial listFull listFull listAsk A to confirm the full list.

After leveling, Vendor A's offer carries four open points and its price is no longer the lowest by the same margin. None of this was on the price sheet. It was in the covering letter, the exceptions list and in what the offer did not say.

What is the purpose of bid evaluation?

The purpose of bid evaluation is to choose the offer that meets the requirement at the best overall value, and to be able to show why. Bid leveling serves that purpose. It stops a buyer from awarding to a price that looks low only because scope is missing, and it gives every vendor the same fair test against the same baseline.

How OdysseyGPT does the technical bid leveling

Reading every offer against every requirement is the slow part. Technical Bid Evaluation (beta) does that reading. You give it the customer specification, the datasheet if there is one, and the supplier offers. It returns:

  • One evidence table across all suppliers, one requirement per line.
  • Each supplier's response to each requirement, cited to its offer.
  • Declared deviations, undeclared deviations, gaps and qualified responses.
  • Draft clarification questions for each supplier.
  • A CSV or JSON export to carry into your leveling sheet.

In the pump example, the excluded baseplate, the silent test and the vendor-standard paint would each appear as a cited line. Your engineers review each finding and decide what to do with it.

Run a past enquiry through it

Choose an enquiry you have already leveled by hand. Send the specification and the offers. On the call you compare the evidence table with your own sheet, line by line.

Request a demo

See it on your own documents

Level your next bid with the reading already done

Bring the enquiry documents and two or three vendor offers. You leave the demo with a cited table of deviations and gaps for each vendor, and a clear view of how it fits your bid tab.

Request a demo

Frequently asked questions

What does it mean to level a bid?

To level a bid is to adjust it so it can be compared fairly with the others. You find what the bidder excluded, added or changed, then clarify or price each difference. When every bid covers the same scope, terms and specification, the bids are level and the prices can be compared directly.

What is a bid leveling sheet?

A bid leveling sheet is a table with one column per bidder and one row per item: base price, scope, deviations, gaps, testing, documents, delivery, terms, adjustments and the leveled total. It shows how each price was adjusted and why. The sheet in this guide is written for equipment packages and can be copied.

Where can I get a bid leveling template?

Copy the leveling sheet in this guide into a spreadsheet, or start from our [bid tabulation template](/resources/templates/bid-tabulation-template). Add rows for the items that matter on your package, such as witnessed tests, spare parts and vendor documents. Keep a source and a reason against every adjustment you make.

What is the purpose of bid evaluation?

The purpose of bid evaluation is to pick the offer that meets the requirement at the best overall value and to record the reasons. It protects the buyer from a low price that hides missing scope, and it treats every bidder the same way by testing each offer against one baseline.

What is the difference between bid leveling and bid tabulation?

Bid tabulation lays the bids out side by side as they were received. Bid leveling adjusts them so they are comparable. In practice you tabulate first, level second and then update the tabulation with the leveled figures. See the [bid tabulation guide](/resources/guides/bid-tabulation) for the layout.

References

ISO 9001:2015 Quality management systems. Requirements

International Organization for Standardization

API Standard 610: Centrifugal Pumps for Petroleum, Petrochemical and Natural Gas Industries

American Petroleum Institute